Following are questions from a project team (Pravin) and my responses. Note that your mileage may vary, but much is generally applicable.

P1 Pravin's first set of questionstgradinf.gif (242 bytes)Pravin
L1 My answers to his first set of questions
P1 Pravin's second set of questions
L1 My answers to his second set of questionstfaculty.gif (185 bytes)
Dr. Whitman

tgradinf.gif (242 bytes)P1)UOB1 - It decides type of product order ( Custom product or standard product)

tfaculty.gif (185 bytes)L1) Fine

tgradinf.gif (242 bytes)P2) I am assuming Joe as the resource for the UOB1. Is it right?

tfaculty.gif (185 bytes)L2) No resource required to 0 processing time.

tgradinf.gif (242 bytes)P2) After the UOB1, fan out junction J1 decides the product type. I would like to know probability for that.

tfaculty.gif (185 bytes)L2) Assume 10% custom parts (notincluding the later decision of custom parts)

tgradinf.gif (242 bytes)P1) UOB123 - In generate custome order, this UOB considers acceptence of the custom order.

tfaculty.gif (185 bytes)L1) TRI(1,1.5,7) in DAYS to determine acceptance (45%) acceptance rate.

tgradinf.gif (242 bytes)P2) I am assuming Joe as the resource for the UOB123. Is it right?

tfaculty.gif (185 bytes)L2) No, no resource is required (it is the individual customers who do this

tgradinf.gif (242 bytes)P1)UOB36 - It is in production process. It checks sources for the products. (Single source/Multi source)

tfaculty.gif (185 bytes)L1) Fine

tgradinf.gif (242 bytes)P2) UOB130 - Manufacture products.

tfaculty.gif (185 bytes)L2) Fine, In class we might say TRI(3,9,21) days

tgradinf.gif (242 bytes)P2) I would like to know resources for UOB130

tfaculty.gif (185 bytes)L2) None (assume that it has enough to be non-constrained, probably a bad assumption, but not for this model)

tgradinf.gif (242 bytes)P1) UOB68- Ship the product.After recording details of the shipment.  they are shipping the products.

tgradinf.gif (242 bytes)P2) I am assuming TRI(0 0 0) for the UOB68.

tfaculty.gif (185 bytes)L2) Shipping has no time, so you are correct. (although, constant time of 0 would be simpler)

tgradinf.gif (242 bytes)P1)UOB49- (In receiving) After inspecting parts, they are sending those to inventory and production.

tfaculty.gif (185 bytes)L1) Fine